How a new or replacement system gets approved
In Ohio, nobody may install a new or replacement septic system, or alter an existing one, without an installation or alteration permit from the local board of health (OAC 3701-29-09). Before the board accepts a permit application, it completes a site review. That review includes a soil evaluation and a system design.
The soil evaluation decides what kind of system your lot can take. It must be done by a qualified evaluator, such as a soil scientist or soil classifier certified by the Soil Science Society of America, or a registered sanitarian who works for the health district (OAC 3701-29-07). You can hire an independent evaluator instead of paying the health district to do it. The evaluator visits the site and digs or bores test holes up to 60 inches deep.
The design can be done by a designer working for the health district or one you hire yourself (OAC 3701-29-10). The designer must give you the approximate installation and operating costs of the options that would work on your lot. Ask for that comparison in writing. It's the best cost estimate you'll get before bids.
Once issued, a permit is valid for one year, the board can extend it by six months, and it transfers with the property if you sell. A site review approval stays good for five years if the site and design don't change (OAC 3701-29-09).
Types of systems you may hear about
Ohio's rules describe a system as a set of parts: a septic tank, sometimes a pretreatment unit, and a way to return the treated water to the soil (OAC 3701-29-01). The soil evaluation drives which combination you get.
- Septic tank and leaching trenches. The tank settles solids and passes the liquid to trenches in the soil. This is the conventional system where the soil allows it.
- Mound (sand fill) system. Used where natural soil is too shallow. Sand fill raises the absorption area above the ground surface, and the rules require at least three inspection ports (OAC 3701-29-15, 3701-29-15.1).
- Low pressure or drip distribution. A pump doses the liquid evenly through small holes or drip lines. The rules require one of these on sand fill and may require them on difficult sites.
- Pretreatment units, including aerobic units. Manufactured units that clean the liquid more than a septic tank alone (OAC 3701-29-13). They have mechanical parts that need regular service.
- Discharging systems. Allowed only where returning water to the soil is not feasible, and only with a discharge permit under Ohio EPA's program (OAC 3701-29-06).
Who can install a system
Only a registered installer may install or alter a system (OAC 3701-29-09). Installers register with the board of health in each health district where they work and renew every calendar year. To register, they need to pass the Ohio Department of Health's testing, carry at least $500,000 in general liability insurance, complete six hours of continuing education a year, and file a surety bond (OAC 3701-29-03).
The bond depends on how many systems the installer puts in. An installer who does one household system a year posts a bond equal to the system cost. An installer who does more than one posts a $40,000 bond. The bond protects an owner whose system wasn't installed to code, and a claim must be made within 18 months of the work.
The Ohio Department of Health posts a public list only for installers with the multiple-system bond (ODH). Our ODH-bonded septic installer badge means we matched the business to that list. An installer who does one system a year will not be on it, so no badge does not mean no bond. Either way, ask whether it's registered with your county's health district.
Can you install your own system? Ohio has no general homeowner exemption. A homeowner can register as an installer for work on their own home only, and the board of health may waive the registration fee, the insurance and the bond for that case (OAC 3701-29-03). The waiver is up to each health district, so ask yours first.
When a system has to be replaced
Ohio does not make you replace a system just because the rules changed. An existing system is deemed approved as long as it does not cause a public health nuisance (ORC 3718.012). The law defines a nuisance as, among other things, a system that isn't working because of a missing part or a mechanical or electrical failure, a blockage that backs sewage up, or sewage-like liquid ponding on the ground or reaching surface water. In each case it counts only if the owner doesn't make timely repairs after notice from the board of health (ORC 3718.011).
Repairs must meet the current rules, and an upgrade can be required when flows are added or the house changes substantially (OAC 3701-29-02). For a failing system, the board can agree to a plan that repairs or replaces it in stages (OAC 3701-29-09).
What it costs
We found no current figure from the Ohio Department of Health or a county health district for the typical cost of a new or replacement system. The price depends on the soil, the depth to the water table or bedrock, and the slope of the lot, which is also what decides the system type (Licking County Health Department). The Ohio Department of Health notes that mounds and other specialized systems cost more than a conventional system because of their construction, materials and design work (ODH).
Few installers publish prices. Beagle Hill Services in Frazeysburg listed $1,000 for a test-pit soils study and $450 for a site design and installation plans when we read its website in October 2026. Get at least two written bids for the installation itself, based on the same approved design.
Help paying for it. Ohio EPA funds local health districts to help income-eligible homeowners repair or replace failing systems, with grant-like money that does not have to be repaid. Eligibility runs up to 300% of the federal poverty guidelines, and each health district sets its own priorities (Ohio EPA). Ask your health district whether it has funds this year.
Questions to ask an installer
- Are you registered with my county's health district this year, and is your bond on file?
- Have you installed this type of system before, and can I see one or talk to the owner?
- Does your price follow the approved design, and what is not included?
- Who pulls the permit and schedules the health district's inspections?
- What happens if you hit rock or water that the soil evaluation didn't show?
- What maintenance will this system need, and do you offer a service contract?
Rules checked October 3, 2026.
We used AI tools to help research and draft this guide. Every rule above was checked against the source linked.